on Nov 3, 2016 at 2:33 PM
Approved - IRR CLM835 Correct the sequence of DN0297 (FIRST DAY OF DISABILITY AFTER THE WAITING PERIOD)
Download Attachment IRR CLM835 - Correct the sequence of DN0297 - FIRST DAY OF DISABILITY AFTER THE... 207.05 kB 1 downloads
This clerical IRR is now considered approved following Final
14-Day review without objection.
Business Requirement /
Issue: The title of DN0297 was changed from INITIAL DATE OF LOST TIME
to FIRST DAY OF DISABILITY AFTER THE WAITING PERIOD (IRR CLM780). The
Data Element Reference table by Name should be corrected to present the DN in
the correct sequence of the DN title.
Final Approved Resolution: Correct
the sequence of DN0297 FIRST DAY OF DISABILITY AFTER THE WAITING PERIOD on page
2.3.3 of the 2016 edition of the Claims R3.0 implementation guide.
1 people saw this online
0 people saw this by email